ArmInfo.CJSC "Agarak Copper-Molybdenum Combine" (ACMC) has completed the implementation of an investment project aimed at technological re-equipment of the enterprise. 

A comprehensive modernization program was aimed at capital renovation  of production; technical re-equipment of the quarry and re-equipment  of the factory. The goal of the project is to optimize production,  increase productivity and reduce the total cost of production. 

The program was carried out on the basis of a systematic approach,  which assumed not only the modernization of production, but also the  improvement of the qualifications of the middle management staff of  the plant and the improvement of its organizational structure.   Within the framework of the investment project of CJSC "ACMC", the  re-equipment of the open-pit was carried out, works on the technical  re-equipment of the main mining and transport equipment were carried  out. The main priority was the introduction of Chinese equipment from  LGMG (technological transport), SDLG (loaders), XCMG (graders) and  SHANTUI (bulldozers). The fleet of excavating and loading machines  was renewed, four KOMATSU excavators and three drilling rigs were  purchased. 

In 2020, a project was also developed to increase the  productivity of the enterprise from 3.5 million tons to 4.5 million  tons of ore per year. Within its framework, the plant's concentrating  plant was modernized: a large-scale reconstruction of the crushing  department took place, the old equipment was replaced with METSO  crushers. A new grinding building was built, two new mills  manufactured by TYAZHMASH were installed. 

The capacity of the first tailing dump was also increased due to the  relocation of the Iran-Armenia gas pipeline section, and the  reconstruction of the main pipelines and pumping stations of the 2nd  and 3rd elevations.  The construction of a new pumping station of the  3rd elevation has been carried out.  As part of the technical  project, a recycling water supply system was put into operation,  which significantly minimizes the impact on the environment. The new  system also reduced water use by 30%. 

The amount of investments in the comprehensive modernization  program of CJSC Agarak Copper-Molybdenum Combine amounted to over USD  30 million.  In addition to investment obligations, the company  fulfills all tax and socio-economic obligations. Additionally, within  the framework of the socio-economic development of the Meghri  community 530 thousand US dollars have been allocated in the last  three years. The funds were used to develop urban infrastructures and  to support vulnerable groups of the population.

"The permanent crises that we have all faced since 2008 have led to  unfavorable conditions on the international metal market. In this  context, we saw our task in timely and adequate response to  challenges in order to maintain the need for effective work and  competitiveness. We have successfully completed the investment  project and coped with all the tasks set. A great and difficult work  has been done, for which I would like to thank the entire team of the  plant, "said Andrey Sinyakov, General Director of "ACMC" CJSC Agarak  Copper-Molybdenum Combine is included in the "Armenian" portfolio of  "GeoProMining" assets. The plant is located in the south of Armenia,  on the border with Iran, and is the largest industrial facility in  the Meghri region.

Since 2007, "GeoProMining" has investedmore than 90 million  dollars in the development of ACMC. Currently, the Agarak combine  employs 1150 people. From 2008 to 2020, "Agarak Copper-Molybdenum  Combine" CJSC paid more than 135 million to the state budget of the  Republic of Armenia, including VAT payments. 

As the company informed at ArmInfo's request, at the end of 2020, the  company produced 8,628 tons of copper in copper concentrate against  7,884 tons in 2019,. At the same time, 311 tons of molybdenum in  molybdenum concentrate were produced last year. According to the  results of 2020, the company's revenue amounted to 21.3 billion  drams. According to the results of the current year, the company  plans to produce 10,942 tons of copper in copper concentrate, 391  tons of molybdenum in molybdenum concentrate, and the planned revenue  is expected at 29.9 billion drams (about $ 60 million).