ArmInfo. Major repairs are underway on the M-1 Yerevan- Gyumri-state border interstate highway section. This was reported by the Road Department Foundation.
As noted in the report, major repairs are underway on a 11.5 km long section of the road that runs through the Shirak region from the city of Ashotsk to the Bavra border checkpoint. The work began in 2023. At present, the inner layer of asphalt concrete has been completely laid, and the top layer has been laid on a 4.8 km section. On the remaining sections, work continues on installing the top layer, and curbs are being installed. After asphalting, the road will be equipped with safety elements. Completion of the work is scheduled for autumn.
The contract value of the construction work is about 2 billion 338 million drams. Major repairs are being carried out at the expense of the RA state budget.